Guidelines For Microsoft Office Project
Saturday, October 4th, 2008The Guidelines below were written with the Microsoft Office Project Professional tool in mind, but can be adapted to other scheduling software tools as well.
1) As much as possible, Summary tasks should be deliverables, in noun form, and CAPITALIZED.
2) The last line of each section which has 3 or more tasks should be ‘<deliverable [...]